HA. Thuraakunu
| Started Operating: |
15th Oct, 2001 |
| No. of Staff: |
6 |
| Peak demand: |
31 KW |
| Installed Capacity: |
138 KW |
|
HA. Hoarafushi
| Started Operating: |
13th Aug, 2000 |
| No. of Staff: |
9 |
| Peak demand: |
172 KW |
| Installed Capacity: |
525 KW |
|
HA. Dhidhdhoo
| Started Operating: |
23rd Apr, 1994 |
| No. of Staff: |
11 |
| Peak demand: |
220 KW |
| Installed Capacity: |
680 KW |
|
HDH. Hanimaadhoo
| Started Operating: |
3rd Sep, 1992 |
| No. of Staff: |
12 |
| Peak demand: |
162 KW |
| Installed Capacity: |
520 KW |
|
HDH. Kulhuduffushi
| Started Operating: |
14th Apr, 1988 |
| No. of Staff: |
20 |
| Peak demand: |
692 KW |
| Installed Capacity: |
1920 KW |
|
SH. Milandhoo
| Started Operating: |
16th Sep, 2000 |
| No. of Staff: |
11 |
| Peak demand: |
115 KW |
| Installed Capacity: |
246.40 KW |
|
N. Velidhoo
| Started Operating: |
31st Dec, 1997 |
| No. of Staff: |
12 |
| Peak demand: |
161 KW |
| Installed Capacity: |
336 KW |
|
R. Hulhuduffaaru
| Started Operating: |
11th Jul, 1997 |
| No. of Staff: |
11 |
| Peak demand: |
113 KW |
| Installed Capacity: |
309 KW |
|
B. Eydhafushi
| Started Operating: |
14th Mar, 1995 |
| No. of Staff: |
12 |
| Peak demand: |
220 KW |
| Installed Capacity: |
600 KW |
|
LH. Hinnavaru
| Started Operating: |
10th Aug, 2003 |
| No. of Staff: |
8 |
| Peak demand: |
206 KW |
| Installed Capacity: |
525 KW |
|
N. Holhudhoo
| Started Operating: |
28th Jan, 2004 |
| No. of Staff: |
8 |
| Peak demand: |
116 KW |
| Installed Capacity: |
268 KW |
|
LH. Naifaru
| Started Operating: |
15th Mar, 1995 |
| No. of Staff: |
13 |
| Peak demand: |
345 KW |
| Installed Capacity: |
600 KW |
|
K. Kaashidhoo
| Started Operating: |
9th Nov, 2001 |
| No. of Staff: |
8 |
| Peak demand: |
130 KW |
| Installed Capacity: |
438.4 KW |
|
K. Thulusdhoo
| Started Operating: |
18th Jul, 1984 |
| No. of Staff: |
13 |
| Peak demand: |
182 KW |
| Installed Capacity: |
260 KW |
|
K. Himmafushi
| Started Operating: |
15rd May, 2002 |
| No. of Staff: |
8 |
| Peak demand: |
252 KW |
| Installed Capacity: |
650 KW |
|
K. Maafushi
| Started Operating: |
26th May, 1997 |
| No. of Staff: |
12 |
| Peak demand: |
490 KW |
| Installed Capacity: |
1100 KW |
|
K. Guraidhoo
| Started Operating: |
18th Jul, 1998 |
| No. of Staff: |
11 |
| Peak demand: |
158 KW |
| Installed Capacity: |
368 KW |
|
DH. Kudahuvadhoo
| Started Operating: |
1st Apr, 2003 |
| No. of Staff: |
10 |
| Peak demand: |
230 KW |
| Installed Capacity: |
404 KW |
|
GA. Villingili
| Started Operating: |
23st Sep, 1996 |
| No. of Staff: |
12 |
| Peak demand: |
224 KW |
| Installed Capacity: |
496 KW |
|
GDH. Gadhdhoo
| Started Operating: |
31st Dec, 1994 |
| No. of Staff: |
11 |
| Peak demand: |
116 KW |
| Installed Capacity: |
240 KW |
|
GDH. Thinadhoo
| Started Operating: |
25th Mar, 1988 |
| No. of Staff: |
16 |
| Peak demand: |
502 KW |
| Installed Capacity: |
1236 KW |
|
GN. Fuahmulah
| Started Operating: |
7th Nov, 1992 |
| No. of Staff: |
19 |
| Peak demand: |
660 KW |
| Installed Capacity: |
1800 KW |
|
S. Central Power Station
| Started Operating: |
1st May, 2000 |
| No. of Staff: |
58 |
| Peak demand: |
2210 KW |
| Installed Capacity: |
4250 KW |
|
S. Hulhudhoo Meedhoo
| Started Operating: |
22th Jul, 1997 |
| No. of Staff: |
15 |
| Peak demand: |
230 KW |
| Installed Capacity: |
495 KW |
|